Dear All,
I am little bit confused in deciding which MRP strategy (10 or 40) should be used for the below mentioned scenario.
client is receiving three months rolling sales plan from the customer next 1 month firmed(80%) and further next two months tentative on 25th of each month. Now they want to run the MRP on 25th for the purchasing raw materials for next month plan and on 1st of every month they get the firmed requirement which was 80% on 25th and they again want to run the MRP for actual production .
Now when they run MRP on 25th system should not consider raw material stock for 25th till last day of current month. System should generate planning requirement for next month plan.
Please suggest.
Regards